Which of the following documents is most likely to be of the LEAST value to a planner/scheduler
when planning a contractor's baseline critical path schedule for the construction of a large high clearance bridge located very near an airport? The contractor has been awarded the contract.
Correct Answer: D
Explanation:
When planning a contractor's baseline critical path schedule for constructing a high-clearance bridge
near an airport, a planner/scheduler must consider documents directly relevant to the project's
execution and constraints. Here's the detailed reasoning: roject Plans and Specifications (Option A):
These documents contain the detailed design, materials, and methods necessary for construction.
They are indispensable for planning the baseline critical path schedule.
Project Geotechnical Report (Option B):
The geotechnical report provides critical information about soil conditions, foundational
requirements, and potential challenges, which significantly influence construction sequencing and
methods.
Regulations Published by the Government Aviation Agency (Option C):
As the project is near an airport, these regulations will likely impose height restrictions, flight path
considerations, and safety requirements. Compliance with these regulations is crucial to avoid
project delays or legal issues.
Government's Report on Future High-Clearance Bridge Projects (Option D):
This document provides information on future projects and does not pertain to the current
construction project. It does not provide actionable data or constraints affecting the planning or
execution of the baseline critical path schedule for the awarded project.
Conclusion: Option D is the least valuable document in this scenario as it does not contribute directly
to the planning or scheduling of the current project.
Reference:
This conclusion aligns with principles outlined in the PSP Study Guide (2019), where the importance
of relevant project documents (e.g., specifications, regulations, and geotechnical data) in the
planning process is emphasized.
Question 2
Which of the following types of delay will NOT result in a time extension and additional
compensation for a contractor?
Correct Answer: A
Explanation:
Definitions of Delays
Excusable Delay: These are delays not caused by the contractor and may be beyond their control.
They can be compensable (entitling the contractor to both time and monetary compensation) or
non-compensable (entitling only time extension). Examples include acts of God or owner-caused
delays.
Non-Excusable Delay: These delays are caused by the contractor, such as poor planning or lack of
resources. Non-excusable delays do not qualify for any compensation or time extensions.
Compensable Delay: A type of excusable delay caused by the owner or their representatives that
entitles the contractor to both time extension and additional compensation.
Non-Compensable Delay: An excusable delay that entitles only time extension but no monetary
compensation (e.g., natural disasters).
PSP Study Guide Reference: The PSP Study Guide emphasizes understanding the types of delays to analyze their impacts on schedules and costs. Non-excusable delays, which result from the
contractor's actions, are clearly categorized as not providing grounds for time extensions or
additional payments.
Analysis for Selection:
Option A: Non-excusable delays do not provide contractors with any extensions or compensation as
they result from the contractor’s responsibility.
Option B: Compensable delays provide both time and compensation and do not match the question's
condition.
Option C: Non-compensable delays, though they provide no monetary compensation, can allow time
extensions under certain circumstances.
Option D: Excusable delays generally entitle contractors to time extensions, with or without
compensation depending on the type.
Conclusion: The correct answer is A. Non-excusable delay, as these delays provide neither time
extensions nor compensation to the contractor.
Question 3
For international projects, currency fluctuation risks are best managed by:
Correct Answer: A
Explanation:
Hedging and escalation protect against currency volatility.
Demo Practice Mode
You are viewing only the questions marked as Demo.