Demo AACE International PRMP Exam Questions

Demo practice questions for guest users.

Section: Practice Mode 5 Questions
Demo Practice
Question 1

A risk analyst estimates a cost item as optimistic $80,000, most likely $100,000, and pessimistic $150,000. Using triangular distribution, what is the expected value? 

Correct Answer: B
Explanation:
For a triangular distribution, expected value is calculated as (Optimistic + Most Likely + Pessimistic) ÷ 3. Here, ($80,000 + $100,000 + $150,000) ÷ 3 = $330,000 ÷ 3 = $110,000. This method gives equal consideration to all three estimates.
Question 2

A project has a most likely activity duration of 20 days, optimistic duration of 14 days, and pessimistic duration of 32 days. What is the PERT expected duration? 

Correct Answer: C
Explanation:
PERT expected duration = (O + 4M + P) ÷ 6. Here, (14 + 4×20 + 32) ÷ 6 = (14 + 80 + 32) ÷ 6 = 126 ÷ 6 = 21 days. PERT is useful when duration uncertainty exists and three-point estimates are available.

Demo Practice Mode

You are viewing only the questions marked as Demo.

BACK TO EXAM