AIWMI CCRA-L2 - AIWMI Certified Credit Research Analyst - Level 2 Certification Examination Exam

Page: 1 / 1
Question #1 (Topic: demo questions)

Scott is a credit analyst with one of the credit rating agencies in Indi a. He was looking in Oil and Gas Industry companies and has presented brief financials for following 4 entities: 

ParticularsA LtdB LtdC LtdD Ltd
Total Income2000240030003500
EBITDA500550650460
Interest100100125130
Total Debt1000140010001500

A.
C Ltd
B.
 A Ltd
C.
D Ltd
D.
B Ltd
Correct Answer: A
Explanation not available for this question.
Question #2 (Topic: demo questions)

Scott is a credit analyst with one of the credit rating agencies in Indi a. He was looking in Oil and Gas Industry companies and has presented brief financials for following 4 entities: 

ParticularsA LtdB LtdC LtdD Ltd
Total Income2000240030003500
EBITDA500550650460
Interest100100125130
Total Debt100014001000


Which of the four entities has best interest coverage ratios? 

A.
C Ltd
B.
 Ltd C
C.
A Ltd
D.
B Ltd
Correct Answer: D
Explanation not available for this question.
Question #3 (Topic: demo questions)

Mark Construction Company (MCC) has bagged a contract for construction of a large dam and hydro power project on river Shivna in Madhya Pradesh (MP). The project is also of relevance from the irrigation perspective due to its location and as per the agreement MCC will have to undertake construction of web of canals, approach road to dam, power house and other ancillary units. MCC is promoted by Mr. Thomas Mark, who is a MP from the ruling party which recently formed government in MP. Historically, MCC has been engaged into construction of rural roads, small bridges and railway platforms on contract basis for the Government. MCC will have a separate special purpose vehicle (SPV) floated for this venture. The hydro power project comes under the public private partnership scheme of the Government of MP, where in the private partner builds owns operates and transfers (BOOT) the hydro power plant. The detailed terms of the hydro power project agreement are as follows: 1. The construction of the dam, canals and hydro power plant shall be undertaken by the contractor. The Government of MP will have to acquire land which will submerge on construction of dam and shall rehabilitate the owners of land. 2. MCC shall have right to operate the hydro power project from date of commencement of commercial operations (DCCO) for a period of 20 years and shall transfer the project to Government thereafter. Further, SPV shall be tax exempt for a period of five years from DCCO i.e. FY17-FY21. 3. The power project is of 600 megawatts (MW) shall comprise 4 units of 150 MW each. The estimated cost of project is about INR3, 500 Million to be spent over a period of 4 year(s) the project is estimated to be commercially operational by April 1, 2016 with two units operational on same day and one unit each will be operational on April 1, 2017 and April 1, 2018. 4. Means of finance:
Table 1: Means of Finance
Means of FinanceINR Million
Government Aid (To be classified as Equity)500
Equity900
Debt2100
Table 2: Project Expenditure & Funding Breakdown
5. Amount if expenditure estimated in various years is as follows:
Funding
Cost of ProjectINR MillionDebtGovt AidEquityTotal
FY13 (April to march)7000250450700
FY1412005002504501200
FY1512001200-1200
FY15400400-400
Project Projections Text
Debt shall bear a fixed rate of interest of 10% and all interest till DCCO shall be added to the principal. The expected principal along with capitalized interest is expected to be INR2,400 Million (i.e. INR2100 Million debt plus INR300 Million capitalized interest). The repayment of the same shall be in 12 equated annual installments starting from FY17. Brief projections for the period of FY17 to FY21 are given below:
Table 3: Financial Projections (FY17 - FY21)
Developments as on March 31, 2015 The project manager for the SPV made following comments at a press conferee on March 31, 2015: As you all are aware, we were running bang on schedule till we last met on December 21, 2014. From today we are just left with one more year to complete the project in time. However, the flash floods which struck our dam site on this March 15, 2015 have created havoc in the region. I shall not point out the loss of lives in the region as you all are well aware of those. Our project has also been badly hit due to the same and we have been assessing the damage over the last one week. After analyzing damage, we have made changes in project schedule. Now we will be making only one unit of 150 MW operational on April 1, 2016 and 1 unit each will be added in each of subsequent year(s). Development as on September 30, 2015 Post the flash floods, lot of environmentalists started raising issues of changes in environment due to construction of large number of dams. A few Public Interest Litigations (PILs) have been filed in various courts. Honorable High Court of MP on September 27, 2015, banned construction of any dams in the region and banned permissions for new dams till next hearing scheduled on November 30, 2015. MCC in its press release has indicated that they will apply to the higher court on the matter. As a credit analyst on March 31, 2012, which of the following sets of risks are you going to put in your credit appraisal note? 
ParticularFY17FY18FY19FY20FY21
Revenue from Power sale600900120013201452
EBITDA %72%68%65%60%60%
Interest Cost240.00220.00200.00180.00160.00
Depreciation175.00175.00175.00175.00175.00
PAT17.00217.00405.00437.00

536.20

A.
Off-take risk, Cost and Time over run risk, lack of management experience in such big projects.
B.
 Lack of management experience in large projects, Exchange rate risks, Cost and time over run risks.
C.
Cost and Time over run risk, lack of management experience in such big projects.
D.
Obsolete technology risk, political risks and Cost and time over run risks
Correct Answer: C
Explanation:
Option C is correct because the case clearly identifies two major risks associated with the project: cost and time overrun risk and lack of management experience in large projects. The hydro power project is a large-scale infrastructure project with an estimated cost of INR 3,500 million and a four-year construction period, making delays and cost escalations highly likely. Additionally, MCC has previously been involved only in constructing rural roads, small bridges, and railway platforms, and has no experience in executing a project of this magnitude. Therefore, the company's lack of expertise in managing such a complex hydro power project represents a significant risk. The other options include risks such as off-take risk, exchange rate risk, obsolete technology risk, and political risk, which are either not mentioned or not supported by the facts provided in the case. Hence, Option C is the most appropriate answer.
Question #4 (Topic: demo questions)

Mark Construction Company (MCC) has bagged a contract for construction of a large dam and hydro power project on river Shivna in Madhya Pradesh (MP). The project is also of relevance from the irrigation perspective due to its location and as per the agreement MCC will have to undertake construction of web of canals, approach road to dam, power house and other ancillary units. MCC is promoted by Mr. Thomas Mark, who is a MP from the ruling party which recently formed government in MP. Historically, MCC has been engaged into construction of rural roads, small bridges and railway platforms on contract basis for the Government. MCC will have a separate special purpose vehicle (SPV) floated for this venture. The hydro power project comes under the public private partnership scheme of the Government of MP, where in the private partner builds owns operates and transfers (BOOT) the hydro power plant. The detailed terms of the hydro power project agreement are as follows: 1. The construction of the dam, canals and hydro power plant shall be undertaken by the contractor. The Government of MP will have to acquire land which will submerge on construction of dam and shall rehabilitate the owners of land. 2. MCC shall have right to operate the hydro power project from date of commencement of commercial operations (DCCO) for a period of 20 years and shall transfer the project to Government thereafter. Further, SPV shall be tax exempt for a period of five years from DCCO i.e. FY17-FY21. 3. The power project is of 600 megawatts (MW) shall comprise 4 units of 150 MW each. The estimated cost of project is about INR3, 500 Million to be spent over a period of 4 year(s) the project is estimated to be commercially operational by April 1, 2016 with two units operational om same day and one unit each will be operational on April 1, 2017 and April 1, 2018. 4. Means of finance: 

Table 1: Means of Finance

Means of FinanceINR Million
Government Aid (To be classified as Equity)500
Equity900
Debt2100

Text Block 1

Means of Finance INR Million Government Aid (To be classified as Equity) 500Equity 900 Debt 2100 5. Amount if expenditure estimated in various years is as follows:

Table 2: Project Expenditure & Funding Breakdown

Funding
Cost of ProjectINR MillionDebtGovt AidEquityTotal
FY13 (April to march)7000250450700
FY1412005002504501200
FY1512001200-1200
FY15400400-400

Text Block 2

Debt shall bear a fixed rate of interest of 10% and all interest till DCCO shall be added to the principal. The expected principal along with capitalized interest is expected to be INR2, 400 Million (i.e.INR2100 Million debt plus INR300 Million capitalized interest). The repayment of the same shall be in 12 equated annual installments starting from FY17. Brief projections for the period of FY17 to FY21 are given below

Table 3: Financial Projections (FY17 - FY21)

ParticularFY17FY18FY19FY20FY21
Revenue from Power sale600900120013201452
EBITDA %72%68%65%60%60%
Interest Cost240.00220.00200.00180.00160.00
Depreciation175.00175.00175.00175.00175.00
PAT17.00217.00405.00437.00536.20
Developments as on March 31, 2015 The project manager for the SPV made following comments at a press conferee on March 31, 2015: As you all are aware, we were running bang on schedule till we last met on December 21, 2014. From today we are just left with one more year to complete the project in time. However, the flash floods which struck our dam site on this March 15, 2015 have created havoc in the region. I shall not point out the loss of lives in the region as you all are well aware of those. Our project has also been badly hit due to the same and we have been assessing the damage over the last one week. After analyzing damage, we have made changes in project schedule. Now we will be making only one unit of 150 MW operational on April 1, 2016 and 1 unit each will be added in each of subsequent year(s). Development as on September 30, 2015 Post the flash floods, lot of environmentalists started raising issues of changes in environment due to construction of large number of dams. A few Public Interest Litigations (PILs) have been filed in various courts. Honorable High Court of MP on September 27, 2015, banned construction of any dams in the region and banned permissions for new dams till next hearing scheduled on November 30, 2015. MCC in its press release has indicated that they will apply to the higher court on the matter. After the developments of March 31, 2015, assuming revenues are directly linked to the power production and the EBITDA margins remain intact for the year, as were projected, compute the revised interest coverage ratio dfor FY17 and FY18? 

A.
 FY17: 0.90; FY18: 1.85
B.
FY17: 1.85; FY18: 2.93
C.
 FY17: 0.49; FY18: 0.97
D.
FY17: 1.80; FY18: 2.78
Correct Answer: B
Explanation:
Option B is correct because the flash floods delayed the commissioning schedule, reducing power generation capacity in the initial years. Instead of operating two 150 MW units in FY17 as originally planned, only one unit becomes operational, while additional units are commissioned in subsequent years. Since revenue is directly linked to power production and EBITDA margins remain unchanged, the revised revenues and EBITDA decrease accordingly, whereas interest expense remains unchanged because the debt obligations are fixed. Interest Coverage Ratio (ICR) is calculated as EBITDA ÷ Interest Expense. Based on the revised projections, the ICR for FY17 is 1.85 times and for FY18 is 2.93 times. Therefore, the correct answer is Option B (FY17: 1.85; FY18: 2.93).
Question #5 (Topic: demo questions)

Scott is a credit analyst with one of the credit rating agencies in Indi a. He was looking in Oil and Gas Industry companies and has presented brief financials for following 4 entities: Two credit analysts are discussing the DM-approach to credit risk modeling. They make the following statements: Analyst A: A portfolio’s standard deviation of credit losses can be determined by considering the standard deviation of credit losses of individual exposures in the portfolio and summing them all up. Analyst B: I do not fully agree with that. Apart from individual standard deviations, one also needs to consider the correlation of the exposure with the rest of the portfolio so as to account for diversification effects. Higher correlations among credit exposures will lead to higher standard deviation of the overall portfolio.

A.
Only Analyst A is correct
B.
Both are correct
C.
Only Analyst B is correct
D.
Both are incorrect 
Correct Answer: C
Explanation:

Option C is correct because Analyst B accurately explains the DM (Default Mode) approach to credit risk modeling. In a credit portfolio, the overall standard deviation of credit losses cannot be calculated by simply adding the standard deviations of individual exposures, as suggested by Analyst A. Such an approach ignores the relationship between different credit exposures. The DM approach requires considering both the individual risk of each exposure and the correlation between exposures, since diversification reduces portfolio risk when correlations are low, while higher correlations increase the portfolio’s overall standard deviation of credit losses. Therefore, Analyst A is incorrect, and Analyst B is correct, making Option C the correct answer.
Download Exam
Page: 1 / 1
Next Page