Demo Oracle 1Z0-1075-26 Exam Questions

Demo practice questions for guest users.

Section: Practice Mode 5 Questions
Demo Practice
Question 1

You are implementing project-driven supply chain functionality. You need to set up movement requeststo issue or transfer project material to manage the inventory associated with projects and tasks. Which two are types of movement requests to issue or transfer project material? 

Correct Answer: A, D
Explanation:
When setting up movement requests in a project-driven supply chain, you need to manage inventory associated with specific projects and tasks. The two correct types of movement requests in this
context are:
Statement A: Transfer project material from one subinventory to another – This is a standard type of
movement request in Oracle Cloud, allowing project materials to be transferred between
subinventories. It is essential for managing inventory tied to specific projects and tasks, ensuring that
materials are available where needed for project execution.
Reference: Oracle Fusion SCM Cloud: Inventory Management Guide describes how material transfers
can be executed between subinventories, including project-based transfers.
Statement D: Perform manual pick for such movement requests using the project material, common
inventory, or inventory from another project – Manual picking for project-specific material is another
supported operation. It allows users to perform manual picks from various sources, such as project
material, common inventory, or even inventory from other projects.
Reference: Oracle Project-Driven Supply Chain documentation explains how manual picks can be
configured to source inventory based on project requirements.
Incorrect Statements:
Statement B: Pick transactions are not interfaced specifically by project costing. Although project
costing is relevant for tracking costs, it is not the driving factor behind pick transactions.
Statement C: There is no concept of creating a movement receipt line with the "Project Costing
widget" in Oracle Manufacturing Cloud.
Question 2

In which three ways does Supply Chain Orchestration enrich supply requests with project details to support outside processing for a project-specific work order? 

Correct Answer: B, D, E
Explanation:
Supply Chain Orchestration (SCO) plays a vital role in managing project-specific work orders, particularly for outside processing. Here’s how it enriches supply requests with project details: Statement B: Expenditure Item Date is set to the requested need-by date and Expenditure Organization is set to the manufacturing plant – In project-specific work orders, Supply Chain Orchestration assigns the need-by date asthe Expenditure Item Date. The Expenditure Organization is typically set to the manufacturing plant handling the work order. Reference: Oracle Fusion Project-Driven Supply Chain documentsthis behavior, showing how expenditure details are linked to the project for costing purposes. Statement D: Supply Chain Orchestration initiates the creation of a requisition with the project details – SCO automatically creates a requisition with all relevant project details, such as project number, task, and expenditure information. This ensuresthat the procurement process is aligned with the project’s financial and material requirements. Reference: Oracle SCM Cloud Supply Chain Orchestration User Guide detailsthe automated creation of requisitions with project data for external processing. Statement E: Expenditure Type is set to the expenditure type associated with the outside processing item – In Oracle Cloud, expenditure types must align with the specific processing items. SCO ensures that the correct expenditure type is applied to the work order and subsequent requisitions. Reference: Project Financial Management guides in Oracle SCM Cloud explain how expenditure types are associated with items, ensuring accurate costing. Incorrect Statements: Statement A: SCO does not initiate the creation of a purchase order without the work order. A work order is essential for processing the outside work, and its absence would disrupt the orchestration process. Statement C: The Expenditure Item Date is notset to the receipt date but rather to the requested need-by date for proper alignment with project scheduling.
Question 3

Which three statements are true about the main areas of Managerial Accounting? 

Correct Answer: A, B, D
Explanation:
In Oracle Manufacturing Cloud and related financial applications, managerial accounting plays a
significant role in tracking and managing costs across supply chain and manufacturing activities. The
following is a breakdown of the correct statements:
Statement A: Receipt Accounting is the application that performs accrual accounting for all types of
receipts – Receipt Accounting is a crucial module in Oracle Cloud that supports the tracking of costs
and performs accruals related to receipts. This includes processes such as procurement receipts,
interorganization transfers, and supplier shipments. This allows organizations to recognize and
account for the expenses associated with these receipts.
Reference: Oracle Cloud SCM Documentation for Receipt Accounting outlines how the system
manages accruals and matches them with purchase orders and invoices.
Statement B: Landed Cost Management gives organizations financial visibility into their extended
supply chain costs – Landed Cost Management is designed to capture additional costs that arise
during the transportation, handling, and processing of goods. This includes costs like shipping,
insurance, and customs duties. By including these in the overall cost, it provides a more
comprehensive view of the actual costs of goods in the supply chain.
Reference: Oracle Fusion SCM Guide, "Landed Cost Management," describes how it aggregates
various indirect supply chain costs to give better financial visibility.
Statement D: Cost method can be defined with granularity down to individual items – In Oracle
Manufacturing Cloud, costing methods can be assigned not only at the organization level but also at
a granular level down to individual items. This provides flexibility in defining different costing
strategies for different products depending on their nature, manufacturing process, or market
conditions.
Reference: Oracle Manufacturing Cloud User Guide explainsthe flexibility in configuring cost
methods at different organizational and item-specific levels.
Incorrect Statements:
Statement C: Supply Chain Orchestration automatically selects the correct process based on userdefined Subledger Accounting rules when a supply creation is initiated – While Supply Chain
Orchestration automates various supply chain processes, it does not select processes based on
Subledger Accounting rules. The orchestration system is more focused on managing and coordinating
supply chain processes rather than determining accounting rules.