Demo USGBC LEED-AP-BD+C Exam Questions

Demo practice questions for guest users.

Section: Practice Mode 5 Questions
Demo Practice
Question 1

What is the minimum number of members of the integrated project team for the Integrative
Process Prerequisite, Integrative Project Planning and Design?

Correct Answer: D
Explanation:
D. Six is the correct answer because the Integrative Process Prerequisite: Integrative Project Planning and Design requires a multidisciplinary integrated project team with representatives from key areas of the project. A minimum of six team members ensures that important perspectives such as architecture, mechanical systems, electrical systems, construction, operations, and ownership are included in the planning and design process. This collaborative approach helps identify opportunities for improving building performance, sustainability, and overall project outcomes from the earliest stages of development.
Question 2

Adesign team is pursuing Indoor Environmental Quality Credit, Indoor Air Quality Assessment. The
building is 1,000 ft2 (93 m2) and has a 10 ft. (3 m) ceiling height. In order to earn the credit, what is the
required volume of supply air for the entire building flush-out?

Correct Answer: C
Explanation:
C is the correct answer because the Indoor Environmental Quality (IEQ) Credit for Indoor Air Quality Assessment requires a total building flush-out based on a standard of 14,000 cubic feet of outdoor air per square foot of floor area. Since the building area is 1,000 ft², the required supply air volume is calculated as 1,000 × 14,000, which equals 14,000,000 ft³. This flush-out process ensures that contaminants from construction materials are removed before occupancy, improving indoor air quality and occupant health, and the calculation is based on floor area rather than ceiling height or total building volume.

Demo Practice Mode

You are viewing only the questions marked as Demo.

BACK TO EXAM