Demo USGBC LEED-AP-Homes Exam Questions

Demo practice questions for guest users.

Section: Practice Mode 5 Questions
Demo Practice
Question 1

Envelope leakage is minimized by:

Correct Answer: C
Explanation:
Minimizing envelope leakage is a critical component of improving energy efficiency in homes, as it
reduces unintended air infiltration and exfiltration through the building envelope. This concept is
addressed in the LEED for Homes Rating System (v4) under the Energy and Atmosphere (EA)
category, specifically in credits related to Air Infiltration and Building Envelope Performance.
According to the LEED Reference Guide for Homes Design and Construction (v4), the primary method
to minimize envelope leakage is to install a continuous air barrier:
EA Prerequisite: Minimum Energy Performance
To reduce air infiltration, projects must include a continuous air barrier system that is sealed at all
penetrations, joints, and interfaces to prevent air leakage. The air barrier must be installed around
the entire building envelope, including walls, roofs, and floors.
Source: LEED Reference Guide for Homes Design and Construction, v4, Energy and Atmosphere
Prerequisite: Minimum Energy Performance, p. 112.
Additionally, the LEED v4.1 Residential BD+C rating system reinforces this requirement:
EA Credit: Air Infiltration
Install a continuous air barrier system to control air leakage through the building envelope. The air
barrier must be airtight, durable, and continuous, with all seams, penetrations, and transitions
sealed.
Source: LEED v4.1 Residential BD+C, Credit Library, accessed via USGBC LEED Online.
A continuous air barrier is a system of materials (e.g., house wraps, sealed drywall, or spray foam)
that forms a complete barrier to air movement, significantly reducing energy losses due to leakage.
This is a proactive design and construction strategy to achieve energy efficiency goals.
Why not the other options?
A . Installing a drainage plane: A drainage plane (e.g., house wrap or rainscreen) is designed to
manage water infiltration and protect the building from moisture damage, not to control air leakage.
While it may contribute to overall building durability, it does not address envelope air tightness.
Reference: LEED Reference Guide for Homes Design and Construction, v4, Sustainable Sites Credit:
Rainwater Management, p. 76, which discusses drainage planes in the context of moisture control.
B . Conducting a blower door test: A blower door test is a diagnostic tool used to measure air leakage
in a building, not to minimize it. It quantifies the air tightness of the envelope (in air changes per
hour, ACH) but does not physically reduce leakage. It is required for verification in LEED v4 (EA Credit:
Air Infiltration) but is not a solution for minimizing leakage.
Reference: LEED Reference Guide for Homes Design and Construction, v4, EA Credit: Air Infiltration,
p. 124.
D . Specifying HERS Grade II Insulation: HERS (Home Energy Rating System) insulation grades refer to
the quality of insulation installation, with Grade II indicating moderate defects. While proper
insulation reduces conductive heat loss, it does not directly address air leakage, which is managed by
the air barrier system.
Reference: LEED Reference Guide for Homes Design and Construction, v4, EA Credit: Insulation, p.
120, which discusses HERS insulation grades but not air leakage.
The LEED AP Homes Candidate Handbook emphasizes the importance of understanding EA credits,
including air infiltration, for the exam, referencing the LEED Reference Guide for Homes Design and
Construction as a key study resource. The handbook confirms that the exam is based on LEED v4,
ensuring the relevance of the continuous air barrier requirement.
References:
LEED Reference Guide for Homes Design and Construction, v4, USGBC, Energy and Atmosphere
Prerequisite: Minimum Energy Performance, p. 112, and EA Credit: Air Infiltration, p. 124.
LEED v4.1 Residential BD+C, USGBC LEED Credit Library, accessed via LEED Online
(https://www.usgbc.org/credits).
LEED AP Homes Candidate Handbook, GBCI, October 2024, p. 12 (references study resources and
exam scope based on LEED v4).
USGBC LEED for Homes Rating System (v4), available via USGBC website
(https://www.usgbc.org/resources/leed-homes-design-and-construction-v4).
Question 2

For a site in a town with a population of 10,000 to qualify under Location and Transportation Credit,
Site Selection, Option 2: Infill Development, what portion of the site’s perimeter must border
previously disturbed land?

Correct Answer: C
Explanation:
The LEED for Homes Rating System (v4) outlines the requirements for the Location and
Transportation (LT) Credit: Site Selection, which includes Option 2: Infill Development. This credit
encourages development on sites that minimize environmental impact by utilizing previously
disturbed or developed land. For a site to qualify as infill development, a specific portion of its
perimeter must border land that has been previously disturbed.
According to the LEED Reference Guide for Homes Design and Construction (v4), the requirement for
Option 2: Infill Development is as follows:
Option 2. Infill Development (1 point)
Select a lot such that at least 75% of the perimeter of the project site immediately borders parcels
that are previously developed or that have been graded or otherwise altered by direct human
activities.
Source: LEED Reference Guide for Homes Design and Construction, v4, Location and Transportation
Credit: Site Selection, p. 54.
This means that 75% of the site’s perimeter must border previously disturbed land to meet the infill
development criteria. The population of the town (10,000 in this case) does not directly affect the
infill development requirement but may be relevant for other LT credits, such as Access to Quality
Transit or Neighborhood Pattern and Design, which consider community size or density. However, for
Site Selection, Option 2, the focus is solely on the perimeter bordering previously disturbed land.
The LEED v4.1 for Homes rating system aligns with this requirement, as it maintains the same infill
development criteria for residential projects under the LT category:
LT Credit: Site Selection, Option 2. Infill Development
At least 75% of the project site’s perimeter must border previously developed or disturbed parcels.
Source: LEED v4.1 Residential BD+C, Credit Library, accessed via USGBC LEED Online.
The LEED AP Homes Candidate Handbook confirms that the exam tests knowledge of the LEED v4
rating system, including the LT credits, and references the LEED Reference Guide for Homes Design
and Construction as a primary study resource. The handbook does not alter the technical
requirements but emphasizes understanding credit intent and compliance paths, such as the infill
development perimeter rule.
Why not the other options?
A . 25%: This is too low and does not meet the minimum threshold for infill development, which
requires significant adjacency to previously disturbed land to ensure compact, sustainable
development.
B . 50%: While closer, 50% still falls short of the 75% requirement, which is designed to prioritize sites
fully integrated into existing developed areas.
D . 100%: Requiring 100% of the perimeter to border previously disturbed land is overly restrictive
and not specified in the LEED v4 or v4.1 requirements.
References:
LEED Reference Guide for Homes Design and Construction, v4, USGBC, Location and Transportation
Credit: Site Selection, p. 54.
LEED v4.1 Residential BD+C, USGBC LEED Credit Library, accessed via LEED Online
(https://www.usgbc.org/credits).
LEED AP Homes Candidate Handbook, GBCI, October 2024, p. 12 (references study resources and
exam scope based on LEED v4).
USGBC LEED for Homes Rating System (v4), available via USGBC website
(https://www.usgbc.org/resources/leed-homes-design-and-construction-v4).
LEED v4.1 for Homes, USGBC, accessed via LEED Online, confirming alignment with v4 infill
requirements.

Demo Practice Mode

You are viewing only the questions marked as Demo.

BACK TO EXAM